HSF III Electrical Work Schedule

Over the coming months, electrical ductbank work will be done to the Health Sciences Facility (HSF) III building.

Phase 1

Work will take place within the HSF III construction site with a slight narrowing of Pine Street in front of the School of Pharmacy from Oct. 24 to mid-November.

Phase 1A

Half of the Josephine Alley, Recycling Center parking lot will be closed for three months starting Oct. 24. Josephine Alley will be closed to through traffic from Nov. 1 to mid-January.

Phase 2

A section of the Lexington Street sidewalk (north side) will be closed for one week on the west side of Koesters Lot. Some parking spaces will be temporarily relocated from Nov. 1 to mid-December.

Phase 3

The Lexington Street sidewalk (south side) in front of Pascault Row and the grassy area along Pine Street will be closed to pedestrian traffic and will be open only for emergency egress from Pascault Row from November through March. Residents need to use the south entrances. One lane of parking will be lost during construction.

Phase 4

One lane of parking will also be closed along the Pine Street sidewalk (east side) from Vine Street to Fayette Street from March to May. The Fayette Street roadbed at Pine street intersection will require lane closures.

Need to Know

  • The west side of the Pine Street sidewalk will remain open at all times.
  • The south side of the Fayette Street sidewalk, adjacent to HSF III, will reopen Jan. 1 with new pedestrian lighting.
  • Demolition of the Carter Center by the hospital can start as early as January. The exact date is still to be determined.
  • This schedule may change based on weather or unforeseen site conditions.